Jundee Australia, WA

Location
50km East of Wiluna, WA

Nearest Town
Wiluna, WA

Client
Northern Star Resources Ltd

Commodity
Gold

Contract Type
Fixed & Variable Schedule of Rates

Contract Duration
September 2001 to July 2024

Scope
Declining, lateral and vertical development, stope production using longhole and airleg methods

Byrnecut has undertaken the underground mining operations at Northern Star’s Jundee Gold Mine since 2001.

The Jundee mine was originally started as an open pit operation in 1995, with underground mining commencing in 1997. Byrnecut has performed the underground mining work at Jundee since 2001 through numerous ownership changes, re-tenders and contract extensions.

The Jundee operation actually comprises three separate underground mines – Barton, Gateway and Invicta, each accessed from the base of separate open pits. Byrnecut undertake all underground mining operations, producing approximately 2,100m of development and 185,000 tonnes of ore each month. Byrnecut also operate the crusher feed and surface haulage from each pit to the ROM pad, utilising a fleet of surface loaders and off-highway trucks.

The mine employs an uphole benching method of stoping, with all ore extracted using autonomously guided remote controlled loaders. Byrnecut are market leaders in the utilisation of the Sandvik Automine Autonomous Guidance System for remote controlled loaders. In 2019, Byrnecut's mining team set a world record for single jumbo advance of 754.3 metres in just one month.

The Jundee mine is operated 365 days per year, 24 hours per day with a workforce of around 380 people, working on a fly-in, fly-out roster from Perth.

0
employees
0
pieces of equipment
0M
Adv. / Month (2023)
0t
Ore / Month (2023)
map of lower part western australia

Jundee
Australia, WA

Development Drills Sandvik DL432i / DL431-8C 7
Production Drills Sandvik DL432i / DL431-8C 6
Charge-Up Units Normet Charmec MC605 / MF605 / 1614B 6
Boggers Sandvik LH517i 11
Trucks Sandvik TH663i 11

King of the Hills

Australia, WA

2010 – 2015

completed

Ernest Henry

Australia, QLD

2010 – 2014

completed

Cadia East

Australia, NSW

2010 – 2013

completed

Sinclair

Australia, WA

2010 – 2013

completed

Merlin

Australia, QLD

2010 – 2013

completed

Mariners

Australia, WA

2009 – 2011

completed

Ballarat Gold

Australia, VIC

2008 – 2009

completed

Golden Grove

Australia, WA

2008

completed

Frasers Decline

New Zealand, South Island

2006 – 2010

completed

Telfer

Australia, WA

2005 – Evergreen (LOM)

active

Greenbushes

Australia, WA

2005 – 2007

completed

Ridgeway Deeps

Australia, NSW

2005 – 2006

completed

Tritton

Australia, NSW

2004 – 2008

completed

Nifty

Australia, WA

2004 – 2007

completed

Agnew

Australia, WA

2002 – 2010

completed

Mt Gordon

Australia, QLD

2002 – 2009

completed

Cosmos

Australia, WA

2001 – 2012

completed

Mt Marion

Australia, WA

2001 – 2007

completed

Hill 50 and Morning Star

Australia, WA

1999 – 2007

completed